Cut & Paste does transfer well in to this program. But here is a portion of the outline of the project that moved 70+ cubic yards of rock to the “Mud Hole”.
Rock & Roll Party
June 9th, 2007, Rubicon Trail
Blackwood Canyon, Lake Tahoe
Goal: Prevent further water retention and erosion at THE mud hole
Objectives: Fill holes along trail to the mud hole as needed, Place rocks in hole, Repair Water Bars (Rolling Dips) as needed
Elements: Front loader at rocks to load trailers, Rocks to mud hole a half yard at a time, Rebuild Water Bars
Plans: Decide what holes before the mud hole need filling, Do we try to move boulders?
Logistics: 100 yards of rock one mile from intersection
- Two miles of total distance rocks need to move
- 50 yards of Grapefruit size
- 50 yards of small boulders
- 45 – 60 trips
- 12 – 15 trailers and vehicles to tow them
- 3 – 5 trips per rig
- 1 – 1.5 hours round trip
- 3 – 7.5 hours
- 40+ people to feed
- Sign-in at Blackwood Canyon
- 15 Trailers and tow rigs
- Signage and locations
Timetable:
Friday:
- Loader arrives at rocks
- Move some rock to prep trail
- Show up to claim tent space
Saturday:
- Show up to claim tent space
- Send off early crew to start on trail work
- Sign in and briefing at Blackwood
- Work begins
- Rock moving
- Water Bars
- Lunch break
- Work is finished up
- Dinner and camaraderie
Sunday:
- Move more rock if needed
- Wrap up any loose ends